LNG Operator Demands Integrated Industrial Solutions For Plant StartUp


An operator of an onshore Liquefied Natural Gas (LNG) micro fuel facility sought integrated solutions from a single source contractor. Ongoing activities with multiple construction groups were working compressed schedules in order to ready the facility for a re-purposed product. Direct technical commissioning support became an value target during the early phase of project execution, as pressure testing and torque value verification for 600+ connection joints demanded specific expertise.

LOCATION

San Juan, Puerto Rico

SPECIFICATIONS

  • Operator Type: Downstream

  • Facility Type: Micro Fuel Handling

  • Hydrocarbon Type: LNG

SCOPE OF WORK

Provide torque verification and hydrostatic pressure testing on facility piping.

CHALLENGES

  • 600+ flanges

  • International equipment logistics

  • Working at heights

  • Expedited time line for planning and mobilization

  • Project planning and readiness required efficient communication without a site survey

  • Inadequate pressure testing tie-in points warranted a Management of Change process that required an approved deviation from best practice approaches

  • Due to welded valve placement, standard isolation practices required additional safety measures

PLAN OF EXECUTION

  1. Project Planning & Preparation

    • Reviewed P&ID’s and Isometric drawings from two different engineering firms.

    • Identified manufacturer’s recommended torque values.

    • Planned with client for Customs requirements and entry.

    • Evaluation of tools for SOW completion.

    • Developed a serialized weatherproof torque verification tag containing all relevant data per joint.

    • Reviewed test and cleaning procedures/requirements.

    • Utilized teams of cross trained personnel for both bolting and pressure testing.

  2. Scope Execution

  • Hydraulic Bolting and Flange Management System coordination.

  • On site project management support.

  • Connection integrity management on all joints.

  • Reviewed test packs and verified test pressures, durations, and boundaries.

  • All bolted joints were checked to verify proper joint alignment.

  • All studs were checked for proper material, size, length, and lubrication.

  • All bolted joints were torqued to client specifications.

  • Cleaned systems with compressed air in accordance with client procedures.

TECHNICAL ACHIEVEMENTS & BENEFITS

  • Successful integration with end user and general contractor management, consultants, and field personnel.

  • Provided integrated management and project controls.

  • Reviewed and mapped bolted connections as per design and construction drawings.

  • Changed test medium selection from demineralized water to readily available nitrogen. This provided cost savings on the testing and drying phase.

  • Provided final reports on torqued connections, and applied a tagging system verifying work was performed and completed in accordance with the regulation/standard.


Previous
Previous

Caribbean LNG Operator Calls For Connection Integrity Management Verification

Next
Next

LiquiGel® Pig Offers Safe DeWatering Method For Multi-Diameter Subsea Application