Permian Operator Receives Integrated Expertise For Gathering System Commissioning
Planning and project management across a single source provide bundled solutions that deliver cost effective and schedule sensitive services for three separate Central Gathering Facilities (CGF’s) on an expedited timeline for first oil.
LOCATION
Texas
SPECIFICATIONS
Operator Type: Midstream
Facility: Gathering
Hydrocarbon Type: Liquids
SCOPE OF WORK
Commissioning Support Services:
Hydraulic Bolting
Nitrogen Leak Testing
Hydrostatic Pressure Testing
Dewatering
Desiccant Drying
Project Management
CHALLENGES
(3) Three Central Gathering Facilities
Flange and piping management system
40+ Test packages that required review and approval (per facility)
7,000+ flanges
400+ individual piping systems ranging from 2” – 24” (per facility)
140+ P&ID’s (per facility)
SIMOPS with civil, mechanical, fabrication, utility, I&E, and compressor contractors required work zone identification and workflow mapping
24-hour schedules
Remote work sites
PLAN OF EXECUTION
Project Planning
a. Expedited planning and mobilization
b. Schedule coordination
c. On site project management support
Scope Execution
a. Hydraulic Bolting and Flange Management System coordination
b. Hydrostatic pressure testing and test package management
c. Dewatering and drying to achieve operator specification
d. Coordinate and deploy work crews per competency in relation to the tasks performed and for the reduction of non-productive time (NPT)
e. Manage daily operational changes to meet the needs of the client due to schedule dependencies and general contractor work completion
TECHNICAL ACHIEVEMENTS & BENEFITS
Successful integration with end user and general contractor management, consultants, and field personnel
Provided in-house, integrated services
Provided integrated management and project controls
Projected completed with zero incidents and with no environmental impact
Provided back office and on-site expertise at reading and interpreting P&IDs along with creation of a flange identification/mapping system and creation of test packages
Documented flange data and torque values for 7,000+ flanges spanning three facilities
Achieved zero leaks upon work completion
Increased field labor staff to meet the needs of the client for adding multiple sites and working 24-hour shifts