Project Experiences & Successes

GATE Energy Project Synopsis GATE Energy GATE Energy Project Synopsis GATE Energy

Chevron - Tahiti II Waterflood

GATE provided process / commissioning expertise in the pre-commissioning and dynamic commissioning of the Tahiti II deaeration system (100,000 BWPD Minox).

Scope included planning for the offshore portion of the commissioning and offshore execution with the pre-commissioning contractor including confirmation of design, heat and mass balancing, and performance testing.

Read More
GATE Energy Case Study GATE Energy GATE Energy Case Study GATE Energy

Remaining Life Assessment Of Subsea Jumpers, Flowlines & Risers

GATE was engaged to evaluate the current condition and remaining life of the subsea jumpers and flowline of a deepwater oil and gas facility in the Gulf of Mexico.

The subsea field, which was comprised of multiple oil wells, was produced at a Tension Leg Platform (TLP) with a nominal capacity to produce 100,000 barrels of oil and 50 million cubic feet of gas per day. The subsea and topsides facilities were designed to operate with an expected maximum carbon dioxide (CO2) concentration of 0.15 mole percent from any given producing well.

Read More
Viking Case Study GATE Energy Viking Case Study GATE Energy

Post-IlI Corrosion Assessment & Wax Control Strategy

After an in-line inspection of a pipeline in West Africa, a client discovered significant wall loss in the first three miles of the line. The tool also returned significant wax deposits, casting doubt on the current wax management efforts in place.

The wells producing to the pipeline historically produced H2S; however, the worst offenders were shut-in quickly after it was discovered that they were producing extremely high concentrations of the sour gas.

Read More
Viking Case Study GATE Energy Viking Case Study GATE Energy

Third Party Facilities Assessment

As part of a recent asset acquisition due diligence, GATE was asked to deliver a third party review of the condition of the asset and remaining production life of a floating production system and a fixed jacket.

GATE developed a standardized work process to evaluate the current condition, potential production bottlenecks and future operating expenditure (OPEX) associated with the brown-field producing asset.

Read More
Viking Case Study GATE Energy Viking Case Study GATE Energy

Riser Life Extension Review

The review of the remaining cathodic protection (CP) life of a Gulf of Mexico tension-leg platform (TLP) was undertaken to evaluate the ability of the current systems to support a 20-year life extension. At the same time, the opportunity to include non-destructive riser testing into the life extension program was also identified.

Read More
Viking Case Study GATE Energy Viking Case Study GATE Energy

Steam Plant Piping Corrosion

A steam generating plant supporting an associated thermal recovery project in the Middle East was experiencing through-wall corrosion of carbon steel lines. In some locations this was aggressive enough to corrode through replacement piping in as little as two months.

Read More
Viking Case Study GATE Energy Viking Case Study GATE Energy

Inspection Plan Development For Mothballed Equipment

A South American operator developed plans to return a sulfur recovery unit to service after an initial ten years of service and a further ten years of mothballing due to changes in field production requirements.

The corrosive nature of molten sulfur, carbon dioxide and hydrogen sulfide in the unit, coupled with the expectation of a less than optimum preservation strategy in a littoral offshore environment, generated a large set of integrity risks that needed to be evaluated to determine the feasibility of repairing and reinstating the system for a further ten years of service.

Read More
Viking Case Study GATE Energy Viking Case Study GATE Energy

Hydrate & Wax Blockage Remediation

A West Africa field operator witnessed an abnormal increase in pressure topsides when the flowline circulation pump was used to pump dead oil into the production line. No increase in subsea pressure was observed. Operational history prior to blockage hinted at the possibility of the presence of one or both wax and hydrate blockages in the production line. Depressurization options were limited by the blocked gas lift line.

Read More