101 Mile Pipeline Integrity Assessment & Cleaning
A major midstream gas transmission company required stress corrosion cracking (SCC) integrity assessment services by hydrotesting to remain compliant with regulatory specifications. The project consisted of a single 101.9 mile pipeline with both 24 inch and 26 inch diameter pipe. Significant environmental hazards were encountered from pipeline contaminants. Additionally, unknown to the pipeline operator, the pipeline contained a significant amount of debris.
Location: Texas
Specifications
Diameter: 24 inch & 26 inch
Length: 101.9 miles broken into 11 segments with the longest being 12.47 miles
Scope of Work
Complete pressure test and dewatering of pipeline containing contaminants and debris.
Challenges
High economic impact for an extended outage
SIMOPS
Working near energized pipelines and facilities
Mercury elements required competent decontamination and cleaning procedure
Debris in the line created pig movement challenges
Plan of Execution
Project Pre-planning
Multiple site surveys
Stakeholder planning meetings
Creation of technical procedures
Pipeline Filling
Utilized water already in the pipe to ensure proper water column integrity.
Utilization of appropriate back pressure to mitigate the risk of “air lock”.
Hydrostatic Pressure Testing
24-hour stabilization period.
Pre-planned controlled pressurization and depressurization process.
Multiple data points to monitor pressure and temperature along each testsection.
Pipeline Dewatering
Utilization of carbon and particulate filtration to remove mercury and arsenic.
Utilized frac tanks to drop high level of solids prior to filtration.
Controlled release to maintain back pressure to prevent air lock.
Pipeline Cleaning
Developed progressive pigging program.
Utilized surfactant chemistryand mechanical pigs.
Caliper
Ran a caliper tool on selected sections to determine pipeline geometry.
Pipeline Drying
Achieved customer approved dew point and penetration.
Technical Achievements & Benefits
Multiple integrity tests with no ruptures.
Developed procedures to address mercury and arsenic contamination.
Successful caliper tool run.
Successful integration with end user and general contractor management, consultants, and field personnel. Frequent communication, multiple planning sessions, and highly competent field personnel were key to executing this project.
Project completed with zero incidents and no environmental impact.