Pipeline Decommissioning


LiquiGell® pigs and de-oiling chemistry provide economic solution for multi-phase Gulf of Mexico pipeline decommisioning campaign.

Location: Gulf of Mexico

Pipeline Specifications: 2 - 8 inch: multiple lengths

Background

A GoM operator backlogged various production pipelines for decommissioning. Pipeline product varied from single phase to threephase usage with lengths ranging from 1,800’ to 25,000’. All segments were permitted for abandonment in place, which required a minimum seawater flush volume equal to double the pipeline internal volume. Of importance, each segment needed to follow BSEE regulatory pipeline decommissioning standards.

CHALLENGE

Create an economic solution to properly decommission each pipeline segment per Federal regulatory standards with minimal disruption to normal production operations.

SOLUTION

  1. Provide pipeline flushing and fluid filtering technical expertise. Use a water-based AquaGel Plus pig system combined with a displacement of DynoWash de-oiling solvent to carry out solids near the pipe wall.

  2. Create a multiphase execution approach that would bundle pipeline assets together for lower costs and shorter schedules.

Plan of Execution

  • Interconnect multiple pipeline segments using subsea tie-in points and topside platform tie-in points; work stations included both offshore motor vessels and operator platforms.

  • Displace a 250’ column of AquaGel Plus into each pipeline segment for clean product seperation.

  • Follow with a 500’ column of DynoWash cleaning solvent into each pipeline segment.

  • Calculate designed flushing volumes using filtered seawater.

  • Receive and filter all fluids in front of and including the AquaGel Plus and DynoWash de-oil displacement.

  • Discharge all filtered fluids overboard per BSEE regulations.

  • Return the pipeline back over to the operator for separation and burial operations.

Technical Achievements & Benefits

  • Utilized the same tie-in points and equipment for both the AquaGel Plus displacement and the seawater flushing operations.

  • No additional on-site equipment or pig launchers/receivers were needed for chemical components.

  • Mitigated operator’s concerns of pipeline structural integrity with LiquiGel® pig system.

  • LiquiGel® pig system transversed multi-diameter pipeline segments, thus enabling multiple pipeline segments to be bundled for flushing operations. This reduced project costs by shortening the original project schedule and utilizing fewer offshore motor vessels.

  • De-oiling cleaning system encapsulated the solids and allowed trailing pig system to suspend and carry out of pipeline system.

  • LiquiGel® pig and pipeline cleaning system decreased project schedule by mitigating static sheen test failure.


Previous
Previous

16-Inch Pre-Commissioning

Next
Next

Gas Storage