Project Experiences & Successes

BlueFin Case Study GATE Energy BlueFin Case Study GATE Energy

Pipeline Evacuation & Assessment

A GoM operator witnessed a leaking 6” pipeline. Upon repairing the visual leak and attempting to perform a successful hydrostatic pressure test a second non-visual leak occurred, ultimately resulting in extended production loss.

In order to perform a second assessment and bring production back online, the pipeline assessment required a 100% fluidpacked volume of seawater to ensure an oxygen-free environment.

Read More
BlueFin Case Study GATE Energy BlueFin Case Study GATE Energy

6-Inch Re-Assessment

A midstream company operating a high pressure gas pipeline required assessment services in order to maintain regulatory compliance. The said pipeline asset was considered unpiggable for ILI technology. In order to comply with regulatory guidelines for an MAOP verification, the company demanded a hydrostatic pressure test assessment.

Read More